Japan's Nuclear Fuel Cycle Program—An Economic Failure Providing No Energy for Japan

10 July 2006
Japan's nuclear fuel cycle program has been under development since 1956. Despite several trillion yen (tens of billions of dollars) of ratepayer and taxpayer money spent, the program fails to provide any electricity to the public.

Japan's nuclear fuel cycle program is comprised of the development of fast breeder reactor technology, use of mixed (plutonium and uranium) oxide fuel in commercial nuclear power plants, and reprocessing of spent nuclear fuel. None of these have attained commercial-scale use.

The Fast Breeder Reactor Program

Japan's fast breeder reactor (FBR) program begun under Japan's Long-Term Program for Research, Development and Utilization of Nuclear Energy (LTP) was originally scheduled to attain commercialization in the 1970's. So far the date for commercialization has been postponed 7 times. Present plans under the Framework for Nuclear Energy Policy is to “strive for the commercial use of FBRs from around 2050,“ a 70-year delay from the original plan.1

The fast breeder reactor development program has so far produced only one hour of electricity. This occurred on August 29,1995 when Monju, the prototype fast breeder reactor (located in Fukui prefecture) generated electricity for an hour at 5% output.2 Monju had a sodium leak and fire accident 3 months later on December 8, 1995 and has been shutdown since then. The reactor is being refurbished and re-start is scheduled for spring of 2008.

To date about 1 trillion yen (about $9 billion U.S.) of taxpayer and ratepayer money has been spent on the fast breeder reactor development program.

No design or site has been selected for the demonstration fast breeder reactor.

Year of LTP Planned date of Commercial Implementation of FBR

1956———-
1961———-1970's
1967———-1985-90
1972———-1985-95
1978———-1995-2005
1982———-Around 2010
1987———-Around 2020's – 2030's
1994———-By around 2030
2000———-(No date specified)
20053———From around 2050

Japan's Mox Fuel Program For Lwr's

Scheduled to have started in 1999, the use of mixed plutonium-uranium oxide (MOX) fuel in commercial nuclear reactors (light water reactors) is yet to begin. With the exception of minor testing undertaken years ago, the program has to date produced no electricity.

There is considerable opposition to the MOX program both locally and nationally. In 2002 the governors of Fukushima and Niigata prefectures rescinded their prior approval for MOX fuel use at Tokyo Electric's nuclear power plants in their prefectures. Kansai Electric, the second largest utility in Japan has failed twice to go forward with its program, once due to a scandal in 1999 involving quality control data falsification by the British MOX fuel fabricator BNFL, and a second time in 2004, due to rupture of a secondary steam pipe at the utility's Mihama Unit 2 nuclear power plant involving death and injury of workers.

So far, only two prefectures are approving use of MOX fuel.

Commercial Scale Reprocessing

Japan's Rokkasho reprocessing plant, located in Aomori Prefecture in the north of Japan, is now undergoing “active testing“ leading up to commercial operation scheduled for August 2007. The plant is slated to separate plutonium from spent nuclear fuel for use in Japan's nuclear reactors. At a cost of 2.3 trillion yen (about 20 billion U.S.) to ratepayers, it is said to be the most expensive plant ever built in the history of the world.

Choosing the reprocessing option and operating the Rokkasho reprocessing plant will cost 19 trillion yen (about $160 billion U.S.), far more than disposing without reprocessing.4 Critics say it will cost far more.

A second reprocessing plant will be needed for the spent fuel that Rokkasho cannot handle. This is estimated to raise costs to 43 trillion yen (about $375 billion U.S.).

Continuing the reprocessing program will mire Japan in a quagmire of higher nuclear power costs, increased plutonium surplus, and snowballing nuclear waste headaches.

Rokkasho's operation constitutes a violation of Japan's 1997 pledge to the IAEA not to accumulate a plutonium surplus.5 Japan already has over 42 tons of separated plutonium stockpiled in Europe and Japan, so any additional plutonium separated at Rokkasho is not needed and will continue to accumulate on site for years.

Public Opposition And Safety Concerns

Besides the problem of nuclear proliferation, Japan's nuclear program poses a safety and environmental problem.

In Fukui prefecture where the Monju prototype reactor is located, primarily out of safety concerns, nearly a quarter of the region's population has signed a petition seeking that the reactor never be operated again.

According to a survey by Aomori prefecture where the Rokkasho reprocessing plant is located, 81.6% of its population is uneasy (feels anxious about the nuclear fuel cycle and nuclear power facilities in the prefecture.6

Aomori is a major agricultural and marine products producer. In February of this year the prefecture announced that radiation levels in the region's rice will rise to twice the present background level with Rokkasho reprocessing plant operation. Levels in seaweed would increase 2000 times. Major supermarkets in central Japan have said they won't buy the products even if contamination levels are low.

Repeated technical bungling by Rokkasho's owner-operator, Japan Nuclear Fuel, Ltd. since the start of testing, has resulted in the Japanese government, the Aomori governor, and the Aomori legislature coming down hard on the company. A special legislative session will be held shortly, solely on JNFL-generated woes.

In Iwate prefecture just south of Aomori, 15 municipalities have petitioned Aomori prefecture because of safety and environmental concerns about the Rokkasho reprocessing plant.

There is considerable citizen opposition to the MOX fuel utilization plan in LWRs. One of the issues involves safety concerns about Japanese utilities intending to load one-quarter of the core with MOX fuel to high burn up levels without undergoing testing at the same or equivalent reactors.

Of the four significant nuclear accidents in Japan during the past decade, three–including one that required evacuation of the public–were at nuclear fuel cycle facilities. In short, the nuclear fuel cycle is giving a bad name to Japan's entire nuclear power program.

Economic

According to its current balance sheet, the owner operator of the Rokkasho reprocessing plant, Japan Nuclear Fuel, Ltd. is 2.5 trillion yen (about $10 billion U.S.) in debt.7

Can Japan Cooperate In GNEP?

GNEP could have a significant impact on Japan's fuel cycle policy, and raises serious questions about the proliferation risks associated with Japan’s fuel cycle program. For example, the reprocessing used at Rokkasho is considered a proliferation risk under GNEP. GNEP also appears to recognize the proliferation risks associated with the fast “breeder“ reactors that Japan is developing as well. The technology breeds weapons-grade plutonium as it operates.

GNEP proposes that “fuel supplier states“ will reprocess other countries' spent fuel, but Japan does not have the capacity to reprocess all its own spent fuel, let alone take on any fuel from overseas. Since the Japanese government cannot even secure a site for Japanese highly radioactive reprocessing waste, even if the domestic reprocessing capacity problem were solved, Japanese prefectures and local governments will oppose the import of foreign fuel.

GENP also has serious implications the financially strained Japanese electric utilities can ill afford. The Japanese government is not in a position to make a substantial contribution to GNEP's purported aims. Like its contribution to the “coalition of the willing“ in Iraq, its contribution to GNEP will be purely symbolic— a house of cards.


Footnotes

1.
Framework for Nuclear Energy Policy (Tentative Translation), October 11, 2005, Japan Atomic Energy Commission, p.29.
2.
PNC, August 29, 1995.
3.
The Long Term Program for Research, Development and Utilization of Nuclear Energy was renamed the framework for nuclear Energy Policy in 2005.
4.
The 19 trillion yen cost was submitted by the Federation of Electric Power Companies (FEPCO) to the Subcommittee to Study Costs and other Issues of the Electricity Industry Committee of the Advisory Committee for Natural Resources and Energy. (2005). It is the amount required to operate the Rokkasho reprocessing plant for 40 years, including MOX manufacture. The Rokkasho reprocessing plant is to reprocess 32,000 tons of spent nuclear fuel. A second reprocessing plant is not taken into account in this cost calculation. Consideration of a second reprocessing plant is scheduled to begin in 2010. Operations are scheduled to begin before the current Rokkasho reprocessing plant stops in 2045. Size and amount to be reprocessed is not yet decided.
5.
Statement submitted by the Japanese -government to the IAEA. In 1997.
6.
Poll undertaken by Aomori prefecture September 25 – October 14, 2003.
7.
JNFL financial report of assets and liabilities, March 31, 2006.

Similar Posts

  • Fukushima Prefecture Energy Policy Review Committee Interim Report

    19 September 2002 Consultation Procedures for Citizens of Fukushima Prefecture and Others on the "Interim Report" Administrative OfficeEnergy Policy Review Purpose: A consultation is being undertaken to seek views on the "Interim Report" of this Energy Policy Review in order that the views of Fukushima Prefectural citizens etc. will be reflected in future energy policy [of this nation]. Who Can Submit: Citizens and organizations not limited to Fukushima Prefecture. How the "Interim Report" will be made public[Libraries, home page, through the media, etc.] Consultation Period: October 1 – November 30, 2002 Method of Submission: Mail, fax, email : energy-g@pref.fukushima.jp How Submissions Will Be Handled. Placed on home page Green ActionSuite…

  • Fukushima Prefecture Energy Policy Review

    In February 2001, Governor Eisaku Sato of Fukushima Prefecture announced that he would not allow the use of MOX fuel in Fukushima Prefecture in spite of earlier promises to the national government and Tokyo Electric to allow the pluthermal program to proceed. At the same time, Governor Sato announced his intention of setting up an Energy Policy Review Committee to examine the entire national energy policy from the perspective of an energy producing prefecture. After listening to the views of twelve prefectural citizens on 31 May 2001, the committee proceeded to hear the views of eight lecturers. On October 25, Professor Hitoshi Yoshioka, expert committee member of Japan’s Atomic Energy…

  • Fukui citizens’ letter to Tokyo British Embassy concerning the falsified BNFL MOX fuel shipment back to Britain

    H.M.. Ambassador Stephen GomersallBritish Embassy in Japan1 Ichiban-cho,Chiyoda-ku Tokyo 〒102-8381 Japan 1 July 2002 Dear Ambassador Stephen Gomersall: On 14 June, a BNFL vessel from the United Kingdom arrived in Takahama to take back the “falsified data MOX fuel”. To us in Takahama, we feel as though this will break our hearts. The reason is, if the falsified MOX fuel is returned to the United Kingdom, it could result in further MOX fuel fabrication which could then lead to forced implementation of the pluthermal programme at the Takahama nuclear power plant, and as a result of BNFL fabricating new fuel, the Sellafield region will be, as in the past, forced…

  • Tokyo Electric Scandal Updates

    Tokyo Electric Scandal Update Number 17Date: October 26, 2002 Contents: METI to order one year shutdown of Fukushima Dai-Ichi Unit 1 Operation status of TEPCO reactors Leaked documents reveal alpha nuclide emissions from Fukushima Dai-Ichi Unit 1 & 2 between 1979 and 1981 Tokyo Electric Scandal Update Number 16Date: October 11, 2002 Contents: Aomori governor threatens to halt SNF imports Fukushima legislature passes motion declaring: "Pluthermal Program will not be implemented in Fukushima" Tokyo Electric announces damaged CRDM guide tubes in Fukushima Dai-Ichi Unit 4 reactor Tokyo Electric Scandal Update Number 15Date: October 9, 2002 Contents: (1) Fukushima governor meets Prime Minister Koizumi and calls for reconsideration of nuclear fuel…

  • Green Action Work – May 2023 ~ April 2024

    Lawsuits / Webinars / Submissions / Symposiums / Booklets / Leaflets / Protest Statements The January 1, 2024 Noto Peninsula Earthquake proved yet again that Japan must rid itself of nuclear power reactors In 2003, Noto Peninsula citizens won a hard-fought 28-year battle to stop a nuclear power plant complex from being built in Suzu town, located on the tip of Noto Peninsula. On January 1,2024, Suzu suffered a devastating earthquake. The land around the proposed site elevated 2 meters. Over the years, Green Action was part of the movement to stop the siting of this plant. On February 19th, Green Action organized this press conference at the Foreign Correspondents’…

  • Foreign Correspondents’ Club of Japan Press Conference: MOX Fuel Shipment 2009– Issues and Controversies/Japan’s Failed Nuclear Fuel Cycle

    Japan’s Plutonium Program MOX Fuel Shipment 2009: Issues and Controversies MOX Fuel Shipment 2009: Issues and Controversies Presented to the Foreign Correspondents’ Club of Japan by Aileen Mioko Smith (Executive Director of Green Action)Download PDF version (4.3 MB) Japan’s Failed Nuclear Fuel Cycle Japan’s Failed Nuclear Fuel Cycle Presented to the Foreign Correspondents’ Club of Japan by Hideyuki Ban, Co-Director, Citizens’ Nuclear Information Center(CNIC)Download PDF version (270 KB) The text accompanying Hideyuki Ban’s presentation: Japan’s MOX Program and Nuclear Proliferation